Frank and Adele - Pool Deck Project  
Summer 2004

5/15/04 - Got a late start on Saturday. Zach and I had Karate in the morning, then we went to Home Depot to get some 12' 2x6'ers for the deck surface. They were calling for thunderstorms all weekend. I got really lucky. It was beautiful all day Saturday, and as I was finishing up, it started raining. Sunday- same thing. I had to take a break in the afternoon to get a haircut, but it was ok because I had to get some more wood from Home Depot, mostly the wood for the railing. No rain all day Sunday. Also, Sunday morning, Dave (a friend with a backhoe) showed up and dug the hill out where the big deck part will go, and made some of the landscape a little closer to what I want the end result to be, although that has a long way to go... All in all, a very productive weekend.

I REALLY like this walk around. I thought I'd be content with a half walk around, but it will be so much easier to vacuum and skim with the deck all the way around. Maybe next year we'll do the other half.

 
  You always learn as you go, and get very efficient toward the end of a project. Here's what I learned...
I am not a master with the hand circular saw. In fact, I have a difficult time with it. According to the photos in the building plans, they show setting the boards, screwing them down, then chalk-lining, and cutting them. Well, that doesn't work for me. The chalk-lines didn't snap right- they jump, I'm not even sure they snapped where they were supposed to. Here's what it ended up looking like- way off, and I won't risk wasting expensive lumber trying to cut it with the circular saw. SO, what did I do? I set the boards where they were supposed to go, drew a line on the bottom of the boards with a pencil, along the edge. Then I pulled them back up, one by one, and cut them with the miter saw, and set them back in. That worked great. I did the rest of the deck this way. As you can see from the photos, I have to go back and pull the first three sections back up and cut them like the rest. No big deal.
     
 
     
Man, these corners are a pain! All in all, not too bad, but it wasn't easy at first.   Here's what the left side looks like. You can see where I started to cut as I went along starting with the 4th segment.
     
 
This is how far I got by end of day Saturday. I quit a little bit before dusk because it started to lightning, then rain. I have a little more than 1/2 way to go.   Sunday - took most of the day, but I got the whole thing done (all but cutting down the ones along the left). As I said before, ya get real efficient by the end of the job. I found the best way was to cut all the boards, place them down, screw in just the outer edge, do the next one, etc. When it was all done, I went back, drilled the counter-sunk holes, then the kids filled the holes with screws, and I followed them along, drilling them in.

I guess I should put the ladder in now, so the kids can go swimming. They've been very patient while I get this part done. The weather certainly has been good for swimming! This weekend average temp was ~80-85.

     
 

  That little gap really bugged me. So, in the late evening, I put one post up, cut the resin fence to fit, and voila, There it is. Looks just like my photo shopped version on the other page.
The kids were ahead of me, here!    
     

next  
Page:
1 - 2 - 3 - 4 - 5 -6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14 -15
  next

Home


© 2007 DekBrands. The content and plans provided on this site are for consumer use only. They may not be reproduced, copied or disseminated, except for consumer construction, without the written permission of DEKBRANDS. DEKBRANDS and Dek-Block are trademarks of Proshop Plans Co., Inc. Patent No. 5,392,575, 5,953,874, 6,324,801B1, 6,446,403B2, 6,550,201B2, and 6,609,346 Pat. Pend/App. Pend. Manufactured under license.